Reading Bid Documents + Scope Reference

Why this matters

Commercial + larger residential projects come with a scope of work, blueprints, specifications, and addenda. Sub-contractors who can read these documents accurately bid correctly + execute correctly. Misreading the scope means either losing money on a low bid OR being non-competitive on a high bid. This is the field card.

Document hierarchy

When documents conflict, there's an order of precedence (usually stated in the contract):

  1. Modifications + change orders (most recent)
  2. Addenda (issued during bidding)
  3. Agreement / contract (the binding document)
  4. Specifications (written technical requirements)
  5. Drawings (architectural + engineering plans)
  6. Standards referenced (NEC, IPC, IBC, etc.)

When the spec says "Schedule A" and the drawing says "Schedule B", spec wins unless contract states otherwise. Field experience: always submit RFIs (Request for Information) to clarify conflicts BEFORE bidding OR during work.

Drawing types in a bid set

A-series (Architectural):

  • Floor plans
  • Elevations + sections
  • Door + window schedules
  • Finish schedules
  • Detail drawings

S-series (Structural):

  • Foundation plans
  • Framing plans
  • Structural details

M-series (Mechanical / HVAC):

  • Equipment schedule
  • Ductwork layout
  • Piping layout
  • Sequence of operations
  • Controls + zoning

P-series (Plumbing):

  • Fixture layout
  • Drain + vent isometric
  • Water supply layout
  • Gas distribution

E-series (Electrical):

  • Power plan (outlets, equipment)
  • Lighting plan
  • Riser diagram (panel + service)
  • Schedules (panel, fixture)

FP-series (Fire Protection): sprinklers, fire alarm.

C-series (Civil): site, grading, utilities.

L-series (Landscape): site planting, irrigation.

Find your trade's series + read it fully. Then read adjacent series for context (your equipment is on M, but how it's powered is on E; how it's framed is on S).

Reading specifications (CSI MasterFormat)

Spec books are organized in divisions:

  • Division 1: general requirements (permits, schedule, payment, closeout)
  • Division 22: plumbing
  • Division 23: HVAC
  • Division 26: electrical
  • Division 27: communications
  • Division 28: electronic safety + security
  • Division 33: utilities
  • (and so on)

Within each division:

  • Section ##-##-##: specific products / installation requirements
  • Part 1: general (definitions, submittals)
  • Part 2: products (materials, equipment, manufacturers)
  • Part 3: execution (install procedures, testing, cleanup)

A typical bid requires reading 5 - 20 sections relevant to your trade.

Critical sections to read carefully

General Conditions (Division 1):

  • Project schedule
  • Substantial completion date
  • Liquidated damages
  • Insurance + bonding requirements
  • Pay application process
  • Lien rights / waivers

Your division's sections:

  • Acceptable manufacturers (the "or approved equal" clause matters)
  • Required submittals (shop drawings, samples, product data)
  • Testing requirements
  • Warranty terms
  • Coordination with other trades

Skipping these = unpleasant surprises during execution.

"Furnish + install" vs "install only" vs "furnish only"

The scope often distinguishes:

  • Furnish + install (F&I): contractor provides AND installs the item
  • Install only: customer / general contractor provides the item; you install
  • Furnish only: you provide; someone else installs

A bid for "install the rooftop unit" expects the unit to arrive - if YOU need to provide it, your bid was understated.

Read each line item carefully. The verb determines your scope.

Quantity vs lump sum

Lump sum (LS): fixed price for the whole scope. Risk on you for quantity variance.

Unit price: price per unit (per outlet, per linear foot of pipe, per square foot of roof). Risk on the GC; final cost = unit × actual quantity.

T&M with cap (time + materials, not to exceed): hourly rate + materials, capped at a total. Risk shared.

Different sections often use different methods. The "fire alarm" might be lump sum; the "miscellaneous additions" might be unit price.

RFIs (Request for Information)

Before bidding, OR during the bid, OR during construction:

  • Submit RFI in writing (email OR formal RFI form)
  • Reference specific drawing / section / detail
  • Ask a specific question with multiple options if appropriate
  • Don't assume; ask

The RFI process is your protection against scope creep + scope ambiguity. Architects + engineers respond + the answer becomes part of the project record.

Common bid mistakes

Missing addenda: bid issued, addendum changes things, bidder doesn't see it. Submitted bid is now wrong. Always confirm latest addendum before submitting.

Misreading scale on drawings: 1/8" = 1' vs 1/4" = 1' is a factor of 2 in linear measurement, 4x in area. Verify scale.

Skipping the spec details: pulling product details from drawings only, missing manufacturer requirements OR install details in the spec.

Not coordinating with other trades: your duct runs through electrician's wall cavity. Each scoped it; both expect access. Job conflict at install.

Underbidding: low bid wins but leaves you executing at a loss. Honest pricing beats winning + losing money.

Skipping coordination meetings: where ambiguities get worked out. The bidder who attends sees the project differently than the bidder who didn't.

Take-offs (quantity counting)

For your trade's portion:

  • Count fixtures (outlets, registers, fixtures, runs)
  • Measure linear footage (pipe, wire, duct)
  • Calculate area (paint, drywall, flooring)
  • Add waste factor (10 - 20% typical for materials)
  • Add labor estimates per unit

Software helps (PlanSwift, OnScreen Takeoff, ConstructConnect). Manual on small jobs.

Inaccurate take-offs = inaccurate bid. Slow + careful beats fast + wrong.

Submittals + shop drawings

Most jobs require submittals before installation:

  • Shop drawings: detailed drawings of fabricated items (ductwork, electrical panels)
  • Product data: cut sheets for equipment + materials proposed
  • Samples: physical samples for finish materials
  • Schedules: detailed product schedules

The architect / engineer reviews + approves OR rejects. Installation must match approved submittals.

Building this into the schedule + cost matters. Submittal review can take 2 - 4 weeks.

Coordination meetings

Larger projects have:

  • Pre-bid meeting (walkthrough; Q&A)
  • Pre-construction meeting (project kickoff)
  • Weekly progress meetings
  • Specific coordination meetings (when scopes interact)

Attendance is often required by contract. Missing = missing the conversation that shapes the work.

Punch list + closeout

Near completion, the customer / GC inspects + creates a punch list of incomplete or deficient items. Closeout requires:

References

  • CSI MasterFormat (Construction Specifications Institute)
  • AIA contract documents
  • ConsensusDocs forms
  • State construction lien laws