Working With General Contractors Reference

Why this matters

General contractors (GCs) are major customers for many specialty trades - new construction, remodels, additions. Working with GCs differs from direct-to-homeowner: payment terms, scheduling, scope agreement, billing all unique. The tech who navigates GC work well builds steady B2B revenue. This is the field card.

What GCs are

General contractor:

  • Coordinates a construction project
  • Hires + manages subs (subcontractors)
  • Bills the customer / property owner
  • Schedules + sequences work
  • Carries general liability + workers' comp

Their customer: property owner OR developer

Your customer: the GC (not the property owner, even if you're working in their home)

When you're a sub

As subcontractor:

  • GC pays you
  • GC coordinates schedule
  • GC handles customer relationship
  • You execute your trade scope

You're NOT:

  • Directly engaged with property owner for scope decisions
  • Authority on overall project
  • Customer's primary contact

Contract types

Subcontractor agreement:

  • Written contract with GC
  • Scope, price, payment terms
  • Insurance requirements
  • Indemnification language
  • Don't proceed without one for significant work

Purchase order:

  • Specific scope + price
  • Less comprehensive than contract
  • Common for smaller jobs

Bid + acceptance:

  • Your bid; GC acceptance
  • Often via email
  • Acceptable for smaller scope

Scope clarity

Before starting:

  • Drawings + specifications (full set)
  • Specific scope (what you do, what others do)
  • Boundaries (where your work ends + others begin)
  • Materials supplied by you vs GC
  • Cleanup responsibility
  • Warranties expected

Ambiguous scope = disputes + lost money.

Pricing for GC work

GCs expect:

  • Competitive pricing (they bid out)
  • Hold-up to project budget
  • Change order pricing (separate from base)

Pricing strategy:

  • Fair (not premium; not lowest)
  • Detailed line items
  • Clear what's included / excluded
  • Add change order processes

Direct-to-consumer pricing usually higher than GC sub pricing (different overhead, marketing, etc.).

Change orders

Original scope changes:

  • New scope item
  • Different material
  • Site condition discovered
  • Customer request added

Change order process:

  • Written change order
  • Scope description
  • Price
  • Time impact
  • GC + property owner approval (often)
  • Then proceed

Don't:

  • Do extra work + bill later (often denied)
  • Modify scope verbally
  • Trust "GC will pay" without paperwork

Scheduling

GC schedules subs:

  • Sequence matters (you can't do duct before walls framed)
  • Coordinate with other trades
  • "Pulled" when site ready
  • "Released" when your work done

Best practices:

  • Be available when called
  • Show up on time
  • Don't promise more than you can deliver
  • Communicate delays immediately

GC builds reputation on hitting schedule; sub who delays threatens that.

Site coordination

On a multi-trade site:

  • Other trades present
  • Coordinate access (you + plumber + electrician can't all be at the same wall)
  • Don't damage others' work
  • Don't cover own work that other trades need access to
  • Respect safety + cleanliness

GC may have site meeting:

  • Pre-job (kickoff)
  • Weekly progress
  • Issue-specific

Material handling

Some GCs supply materials; some expect you to:

  • Materials list per agreement
  • Storage on site (or you bring daily)
  • Theft protection
  • Damage tracking

Check before starting; assumption costs money.

Documentation

For each job:

  • Signed contract / PO
  • Drawings (your copy with notes)
  • RFI (Request for Information) + responses
  • Change orders
  • Photos of work
  • Submittals (manufacturer cut sheets, equipment specs)
  • Permits
  • Inspection records

Document thoroughly; protect against disputes.

Permits

GC often pulls permits; sometimes sub:

  • Specify in contract
  • Don't assume
  • Permit cost + responsibility
  • Inspection scheduling
  • Closeout

If you pull permit: license must match work; inspection delays possible.

Inspections

Code inspector visits:

  • Rough-in (before walls closed)
  • Final
  • Each trade has own inspections

Inspector visits:

  • Be present OR available
  • Address issues directly
  • Don't argue with inspector publicly
  • Document findings + corrections

Cleanup

Sub responsibility:

  • Clean up after own work
  • Remove debris
  • Don't leave materials for others
  • Don't damage finished work

GC handles overall site cleanup; you handle your area.

Payment terms

GC payment typically:

  • Net 30 from invoice receipt
  • Some net 45-60
  • Pay-when-paid clauses (GC pays when GC gets paid; risky for sub)
  • Pay-if-paid clauses (GC only pays if GC gets paid; very risky)

Avoid pay-if-paid contracts when possible; you take risk for GC's customer not paying.

Lien rights

If GC doesn't pay:

  • Mechanic's lien against property
  • State law-specific
  • Notice + filing requirements
  • Effective leverage (property can't be sold OR refinanced)

Standard procedure on commercial projects.

Insurance requirements

GC typically requires:

  • Liability insurance (substantial per-occurrence coverage typical)
  • Workers' comp
  • Auto coverage
  • GC named as additional insured
  • Certificate of insurance (COI) provided

Without insurance: GC can't legally use you.

Indemnification clauses

Watch contract language:

  • "Hold GC harmless"
  • "Indemnify GC for any claims"
  • Make sure you're insuring only your work, not GC's

Some clauses are unenforceable; some are dangerous. Read carefully.

Specific trade considerations

HVAC sub on new construction:

  • Ductwork rough-in
  • Equipment install
  • Refrigerant lines
  • Coordination with framers, drywall, electrical
  • Manual J calculations

Plumbing sub:

  • Underground rough-in (slab homes)
  • In-wall rough-in
  • Fixtures install at end
  • Coordination with framers, drywall, electrical

Electrical sub:

  • Service entry
  • Panel install
  • Rough-in (boxes + wire)
  • Finish (devices + fixtures)
  • Coordination with all trades

Roofing sub:

  • After framing complete
  • Before exterior trim
  • Weather coordination

Specific scenarios

GC asks you to skip permit / inspection:

  • Don't
  • Code violation; your license at risk
  • Refuse politely

GC asks you to charge less than market:

  • Decision based on volume / future work
  • Don't accept loss-leader pricing
  • "I can do for [your price]; can't go lower"

GC asks you to bill higher to property owner than your invoice to GC:

  • Possibly fraud
  • Don't participate
  • Walk away if pressured

GC's project is over budget:

  • Sometimes GC asks subs to cut prices to save the project
  • Negotiable case-by-case
  • Not obligated

GC's customer changes scope:

  • Should be change order
  • GC's customer relationship issue
  • Don't lower your price because customer changed mind

Customer relationship

References

  • ASA (American Subcontractors Association) resources
  • State construction lien laws (varies)
  • ConsensusDocs OR AIA contract documents
  • AGC (Associated General Contractors)
  • Manuall internal: Customer Communication Standards, Service Call Pricing Models