Residential Service Panel Upgrade
Purpose
Define the residential service panel upgrade protocol - replacing an existing main panel with a larger or newer one (typically 100A → 200A upgrade, or any FPE Stab-Lok / Zinsco panel replacement). High-value job; the actual work day is long but planning + permitting determines whether the job lands right or becomes a stressful disaster.
Scope
Applies to:
- 100A → 200A service upgrades
- Like-for-like replacements of recalled panels (FPE Stab-Lok, Zinsco)
- Panel relocations within the same service
Excludes commercial three-phase upgrades + new service installations (separate scope + utility coordination).
Responsibilities
- Master electrician + journeyman team typical
- Permit coordinator files permit + schedules inspection
- Utility company coordinates the meter-drop / re-energize sequence
- Customer is given a clear timeline + power-out expectations
Procedure
Pre-job (1 - 2 weeks before installation):
- Walk-through with customer. Identify panel location, plan for new panel placement (same location ideal; relocation adds complexity).
- Load calculation per NEC 220. Document existing + planned future loads (EV charger, hot tub, addition).
- File permit with the local AHJ. Most jurisdictions require an electrician's permit + a separate utility coordination.
- Coordinate with utility company. They drop the meter for the work + re-energize. Lead time varies widely (a few days to 2+ weeks).
- Customer briefing. "Power will be out approximately 6 - 8 hours on install day. Refrigerator + freezer should be eaten down OR plan for ice. Internet + alarms will be off."
Install day (6 - 10 hours typical):
- Utility drops meter at scheduled time. Verify the meter base remains intact.
- Document existing panel. Photograph every breaker label + every conductor termination before disconnecting.
- Remove existing panel. Disconnect all branch circuits at the panel; cap conductors temporarily for safety.
- Update service entrance if upgrading from 100A → 200A (typically requires larger service-entrance conductors + a new meter base).
- Install new panel. Mount to wall studs; ensure clearance per NEC (30" wide × 36" deep + 6.5' headroom - all required for safe servicing).
- Bond + ground the panel. Main bonding jumper per NEC 250; ground rod or Ufer ground per local code; bond water + gas piping per NEC 250.104.
- Land main service-entrance conductors at the new main breaker. Torque to spec.
- Re-land branch circuits at new breakers. Label each breaker correctly per panel directory (more legible + organized than the original).
- Verify torque on every termination per the panel label spec.
- Inspect everything BEFORE re-energizing. Hot conductors clear of debris, no exposed copper, ground bar complete, neutrals separated from grounds in sub-panels.
- Utility re-energizes meter.
- Energize main breaker + test each circuit individually. Note any issues immediately.
- AFCI / GFCI test on every device installed (some upgrades add these on previously-unprotected circuits per current code).
- Schedule inspection with AHJ for final sign-off.
Post-inspection:
- Address any inspection items within their required timeframe.
- Final customer walk-through showing the new panel + directory.
- Document everything in customer file - panel photos, breaker directory, torque values, inspection sign-off.
Acceptance Criteria
- Permit issued + inspection passed
- Panel mounted per code with proper clearances
- All bonding + grounding complete + documented
- Branch circuits labeled + organized in directory
- All terminations torqued to spec
- Customer signs the field report with photos in file
The service-entrance conductors between the meter base + the panel are LIVE when the utility re-energizes. Test EACH conductor with a meter before final lay-down. A floating meter neutral (uncommon but real) creates lethal voltage between line conductors + ground. NEVER assume "the utility re-energized correctly" - always verify.
References
- NEC Articles 230 (Services), 250 (Grounding), 408 (Switchboards + Panelboards)
- Local AHJ + utility company requirements
- Manufacturer install instructions
- Manuall internal: Annual Whole-Home Electrical Inspection, Whole-Home Surge Protector Installation